Flatiron | Parsons, a joint venture Oakland Airport Connector

In the News

BART Plans to Open Oakland Airport Connector by Thanksgiving Holiday (07/30/14) from NDC Bay Area

BART Board sets fare for BART to Oakland International Airport service(06/12/14)

Renowned artist Gordon Huether fills BART to OAK with color and beauty(04/14/14)

A selection of glass work at the end of the fabrication process An artist's rendering of where the rondels will be installed

Testing to begin on Oakland Airport Connector tracks with new rail vehicles(01/21/14)

BART Unveils AirBART Train Cars(01/21/14)

FPJV Assist with Councilman Larry Reid's Annual Turkey Give-a-way (12/19/13)

Oakland airport BART tram to open in fall 2014 (12/24/13)

BART and Caltrans to Close Southbound Interstate 880 at Hegenberger Road (4/12/13)

BART and Caltrans will close all lanes of southbound Interstate 880 (I-880) at Hegenberger Road on Sunday, April 21 between the hours of 1:30 am and 5:30 am. This early morning closure is necessary to allow crews to construct the Oakland Airport Connector system’s guideway above I-880.  Drivers who must pass through that area will need to follow the detour signs, requiring vehicles to exit at Hegenberger, then detour via Airport Access Road and 98th Avenue in Oakland.

 

BART Awards Grant for Local Apprentice Program (2/26/13)

Local workers make up the bulk of employees building BART’s Oakland Airport Connector (OAC), and thanks to a newly awarded grant, some of those workers will come from an apprentice program aimed at training young Oakland men and women looking to learn a trade. BART officials today announced the decision to award a grant of nearly $34,000 to the Oakland based Cypress Mandela Training Center to employ a young and diverse workforce made up of Oakland residents.

Airport Area News (9/1/11)

Oakland Airport Connector Construction Gets Underway
The Oakland Airport Connector (OAC) has officially moved from the "proposed" stack of projects into the pile of Airport Area projects in "under construction."

 

ABC News 7 Groundbreaking Ceremony Coverage (10/20/10)

Groundbreaking held for BART airport connector
OAKLAND, Calif. -- Politicians, labor leaders, construction workers and religious figures this morning celebrated the groundbreaking on BART's 3.2-mile connector between its Oakland Coliseum station and Oakland International Airport.

Flatiron Construction Press Release (10/5/10)

Flatiron Team Awarded Contract for Oakland Airport Connector
More than 25 years in planning, the $361 million automated people mover project will provide a 3.2-mile connection between the Coliseum BART Station and the Oakland Airport. 

Construction Contracts Awarded (9/23/10)

Oakland Airport Connector Contract Award
BART General Manager awards Construction Contract to the Flatiron/Parsons joint venture team. 

For other public notification announcements, please visit www.bart.gov/oac.

Project Updates

Construction Notification 46: September 2014

Temporary Hegenberger Road Lane Closures and I-880 Lane and Ramp Closures for Netting Removal

Construction Notification 45: August 2014

Daytime Lane Closures on Hegenberger Road between Airport Access Road and San Leandro Street

Construction Notification 44: April 2014

Traffic Signal work on Hegenberger Road at Pardee Drive and Edgewater Drive

Construction Notification 43: January 2014

Vehicle Testing to Begin on Oakland Airport Connector Guideway Tracks

Construction Notification 42: December 2013

Nighttime Closure of San leandro Street at the BART Coliseum/Oakland Airport Station

Construction Notification 41: September 2013

Nighttime closure of 98th Avenue for Guideway Truss Installation

Construction Notification 40: September 2013

Hegenberger Road Lane Closures and Interstate 880 Lane and Ramp Closures at Hegenberger Road

Construction Notification 24: May 2012

Continued Tunnel Construction

Construction Notification 23: May 2012

Guideway Foundation and Column Construction

Construction Notification 21: March 2012

Road Reconfiguration and Guideway Foundation Construction

Construction Notification 20: February 2012

Guideway Foundation Construction

Construction Notification for 2010-2011

Project Schedule

Notice to Proceed November 1, 2010
Design November 2010 - March 2012
Construction April 2011 - Spring 2014
Testing and Commissioning Spring 2014 - Fall 2014
Open to Public Fall 2014